American Constructors Inc World Outreach Expansion Project Case Solution
The building cannot be completed on time as the number of days required for completion of all the remaining parts of the building are 87.25* days and from September 24 to December 14 there are only 81 days (6+31+30+14) which is 7.25 days less from the required amount of time period.
Case Analysis for American Constructors Inc World Outreach Expansion Project
*(87.25 is the sum of the average time required for completion of main tasks; the sanctuary, lobby and the kitchen / bookstore / café) (time period for the main task if further the sum of sub-tasks for each).
Grott’s challenges include the completion of the building which does not seem to be happening in the given time period. He knows that the project cannot be completed without overtime and they will also have to provide incentives to the subcontractors to make them work faster. Additionally, he had to make sure no error or mistake occurred in the timeline.
This problem can be dealt by using crashing network approach; this approach is used to reduce required project time by adding more resources.
Get instant access to this case solution for only $9
Get Instant Access to This Case Solution for Only $9
Standard Price
$25
Save $16 on your purchase
-$16
Amount to Pay
$9
Different Requirements? Order a Custom Solution
Calculate the Price
Related Case Solutions
Get More Out of This
Our essay writing services are the best in the world. If you are in search of a professional essay writer, place your order on our website.